Project Information
Profile
Title:Construction of Evacuation Facilities at Barangay Malaban and Casile, Binan City, Laguna
Description:Evacuation Facilities
Program:Seal of Good Local Governance
Province:LAGUNA
City/Municipality:CITY OF BINAN
Exact Location:Barangay Malaban and Casile, Binan City, Laguna
Year:2017
Category:DRRM
Sub-Category:Evacuation Centers
Beneficiaries:household of the city
Number of Beneficiaries:0
Project Status:Not yet Started
Warning Scheme
| Completed within 1 year | Completed beyond 1 year
| Less than 6 months uncompleted | More than 6 months uncompleted
| More than 1 year uncompleted | Incomplete/Incorrect Data
Dates
Proposed Start Date: January 2019
Proposed End Date: December 2019
No. of Days: 334
Date of Receipt of the NTI:
Actual Start:
Actual End:
No. of Days:
Project Cost
LGU Counterpart: PHP0
PCF Subsidy: PHP5,100,000
Total Project Cost: PHP5,100,000
Project Images
No Image Uploaded.

Uploaded Files
Physical Accomplishment
Date% of AccomplishmentFiles UploadedRemarks
0000-00-00 100.00 % view Uploaded SWA
2018-11-16 0.00 % view Uploaded SWA none
Financial Accomplishment

No financial accomplishments yet

Actions

Comments





Name:
Email:
Message:
(Maximum characters: 1000)
You have characters left.