Project Information
Profile
Title:Construction of Poblacion Drainage Canal
Description:Concreting of 1300 linear meter Reinforced Drainage Canal
Program:Seal of Good Local Governance
Province:ABRA
City/Municipality:DOLORES
Exact Location:Poblacion Dolores, Abra
Year:2016
Category:Millenium Development Goals
Sub-Category:Water and Sanitation
Mode of Implementation: By Administration
Implementing Unit: Local Government Unit
Beneficiaries:General Public
Number of Beneficiaries:0
Project Status:On Going
Dates
Proposed Start Date: 2017-05-04
Proposed End Date: 2017-10-11
No. of Days: 160
Date of Receipt of the NTI: 2017-01-27
Actual Start: -
Actual End:
No. of Days:
Project Cost
LGU Counterpart: PHP0
PCF Subsidy: PHP3,000,000
Total Project Cost: PHP3,000,000
Project Images
Before
During
During
During

Uploaded Files
Physical Accomplishment
Date% of AccomplishmentFiles UploadedRemarks
2017-04-04 0.61 % view Uploaded SWA
2017-05-04 23.93 % view Uploaded SWA
2017-07-04 27.33 % view Uploaded SWA
2017-10-06 65.16 % view Uploaded SWA
Financial Accomplishment

DatePCF Amount Disbursed Files UploadedRemarks
2017-08-24 PHP 693,193.02 view Uploaded SORD
Remaining PCF Balance PHP 2,306,806.98