Project Information
Profile
Title:Construction of Poblacion Drainage Canal
Description:Concreting of 1300 linear meter Reinforced Drainage Canal
Program:Seal of Good Local Governance
Province:ABRA
City/Municipality:DOLORES
Exact Location:Poblacion Dolores, Abra
Year:2016
Category:Millenium Development Goals
Sub-Category:Water and Sanitation
Mode of Implementation: By
Implementing Unit:
Beneficiaries:General Public
Number of Beneficiaries:0
Project Status:Not yet Started
Dates
Proposed Start Date: 2017-05-04
Proposed End Date: 2017-10-11
No. of Days: 160
Date of Receipt of the NTI:
Actual Start:
Actual End:
No. of Days:
Project Cost
LGU Counterpart: PHP0
PCF Subsidy: PHP3,000,000
Total Project Cost: PHP3,000,000
Project Images
Before

Uploaded Files
Project Proposal: Construction of Poblacion Drainage Canal Project Proposal AIP/LDIP: Construction of Poblacion Drainage Canal Annual Investment Plan
Memorandum of Agreement: Construction of Poblacion Drainage Canal Memorandum of Agreement Authority to Purchase (for Vehicle): No uploaded Authority to Purchase yet.
Notice to Implement: No uploaded NTI yet.
Physical Accomplishment
No physical accomplishments yet
Financial Accomplishment

No financial accomplishments yet

Actions

Comments





Name:
Email:
Message:
(Maximum characters: 1000)