Title:CONSTRUCTION OF DRAINAGE CANAL WITH CONCRETE COVER
Description:The total length of the drainage canal is 350 LM. The project will complement the existing drainages
Program:Seal of Good Local Governance
Province:PANGASINAN
City/Municipality:BAYAMBANG
Exact Location:MH Del Pilar Street, Bayambang, Pangasinan
Year:2016
Category:DRRM
Sub-Category:Flood Control
Mode of Implementation: By Administration
Implementing Unit: LGU BAYAMBANG
Beneficiaries:urban population with population area
Number of Beneficiaries:2700
Project Status:Completed
Dates
Proposed Start Date: 2017-06-05
Proposed End Date: 2017-08-08
No. of Days: 64
Date of Receipt of the NTI: 2017-06-02
Actual Start: 2017-06-02
Actual End:
No. of Days:
Project Cost
LGU Counterpart: PHP0
PCF Subsidy: PHP3,000,000
Total Project Cost: PHP3,000,000
Project Images
Before
During
After

Uploaded Files
Physical Accomplishment
No physical accomplishments yet
Financial Accomplishment

DatePCF Amount Disbursed Files UploadedRemarks
2017-11-02 PHP 2,985,000.00 view Uploaded SORD
Remaining PCF Balance PHP 15,000.00view Uploaded Receipt