Welcome


Project Details

Materials Recovery Facilities

The project will house an MRF facility where recyclable materials will be stored in six (6) concrete cubicle for cans, bottles, (white and dark colored), broken bottles and paper. A portion of the structure will station the equipment such as shredder and aerator. This project will also be used as composting facility where compost or organic fertilizer will be produced and sold at low cost to all interested farmers. The major goal of the project is reduction of volume of collected garbage in the locality.

Seal of Good Housekeeping

Sitio Libo, Brgy. Sto. Tomas Sulat Eastern Samar

EASTERN SAMAR

SULAT

2013

Ecological Solid Waste Management

Material Recovery Facilities

By Contract

LGU

-

populace

9997

Completed

Before
During
After
Files

Materials Recovery Facilities Project Proposal

Materials Recovery Facilities Annual Investment Plan

Materials Recovery Facilities Memorandum of Agreement

No uploaded Authority to Purchase yet.

No uploaded Project Completion Report yet.

No uploaded Certificate of Acceptance yet.

No uploaded Final Report of Disbursement yet.

Dates

2013-03-01

2013-08-30

182

2013-2-04

2013-11-06

275

Project Cost

PHP0

PHP1,000,000

PHP1,000,000

Physical Accomplishment
No physical accomplishments yet
Financial Accomplishment

PCF Amount Disbursed LGU Amount Disbursed FI Amount Disbursed Total
No financial accomplishments yet